The National Piers Society Historical Timeline Of Colwyn Bay Pier

November 4, 2020

Work began in 1899 to the design of Maynall and Littlewood of Manchester. The pier opened on 1st June 1900 to a length of 220 feet, including a 2500 seat pavilion. The Bijou Theatre, built in 1916, accommodated 600. In 1922, the main pavilion was burnt down. It was replaced the following year, by the pier’s new owners, the local council. In 1933, the pavilion was once again destroyed by fire and, two months later, a separate blaze wrecked the Bijou Theatre. A replacement pavilion opened in 1934.

Repairs were made to the pier in 1954 and from 1964 onwards. Trust House Forte became owners in 1968, and the structure was refurbished. However, in 1976 THF applied to demolish the seaward end. A 4000 signature petition helped persuade Colwyn Borough Council to refuse permission. Parker Leisure Holdings bought the pier in 1979 and converted the ‘Dixieland Showbar’ into a disco with adjoining bars.

In 1986, it was estimated that repairs to the seaward end would cost £250,000 and, although grants were being sought, a further application for demolition was made in 1987. The pier was put up for sale in 1989 and again in July 1991. The pier was closed and seemed doomed.

Ownership transferred to Mr. and Mrs. Paxman in late 1994 and restoration work commenced. Visitors were admitted during the summer of 1995. The Paxmans lived on the pier but were unable to transform it into a major tourist attraction, and in December 2003 the pier was sold to Mr. Steve Hunt.
Mr Hunt began a programme of refurbishment of the pier but as a private owner, was ineligible for Heritage Lottery Fund or other grants. In 2008, in a highly charged dispute with Conwy Council, Steve Hunt was made bankrupt, something he fought vigorously to get overturned accusing the Council of corruption. In the meantime, management of the pier was vested in trustees, Royce Peeling Green (RPG) but the pier continued to deteriorate and demolition was beginning to be considered.
In 2010, a local support group, the Victoria Pier Pressure Group announced their plans to acquire the Victoria Pier from the trustees and outlined proposals for the pier which include a new cafe, bar, children’s entertainment, fishing facilities and a historic and environmental educational centre. However, with an estimate of £5.5 million pounds to restore the pier, this was clearly going to be a very challenging project.
With Mr Hunt effectively sidelined, but still asserting his rights to the pier, plans began for a submission to the Heritage Lottery Fund. The Council were supportive of the Pier Pressure Group’s proposals and added support came from the Welsh Government Minister who visited the pier in February 2011.

However, not everyone felt that restoring the pier was the best option and in March 2011, the Chairman of the Colwyn Bay Civic Society called for the pier to be demolished. Neverthless, in May 2011 Conwy Council announced that they would try to buy the pier and would be seeking Welsh Government assistance.

Then in June 2011, Mr Hunt, the previous owner started a hunger strike in protest at what he claimed was “overwhelming evidence of wrongdoing” by the council. The local MP, David Jones, persuaded Mr Hunt to give up his hunger strike but said that he felt that Mr Hunt had been ‘airbrushed out of the process’ and that there had been ‘insufficent engagement’ with him.

Also in June 2011, the new not-for-profit company, ‘Shore Thing’, who had already been working closely with the Pier Pressure Group, announced plans to run the pier on a not-for-profit basis, reinvesting profits back into the business.

But the Trustees, RPG, who effectively still owned the pier were becoming increasingly concerned as the pier’s condition became worse with each passing day and pieces began falling off it. Finally, in August 2011, they took the decision to disclaim interest in the pier pursuant to section 315 of the Insolvency Act 1986 and ownership automatically passed to the Crown Estate. Mr Hunt, having now been discharged from bankruptcy, reasserted his claim to ownership of the pier and said he wanted to restore it.

In November 2011, a public consultation was held and Shore Thing’s plans for the restored pier were put on show. These received strong support and in March 2012, a bid went before the HLF Board for £4.9million towards the estimated total cost of £10 million. However, the question of the pier’s ownership was still to be resolved.

Then at the end of March 2012, it was announced that Conwy County Council had bought the Victoria Pier from the Crown Estate with a £36,000 grant from the Welsh Government. This was not without its risks given that the HLF bid had not yet been decided, something that became even clearer when only a few days later the HLF bid was rejected. Nevertheless, Jennifer Stewart, head of HLF Wales, said that they were “impressed with the council’s imaginative plans to transform Colwyn Bay Victoria pier and its art deco pavilion into a much-needed community and tourist centre”. The Council said a new improved Lottery bid would be made and that at least now the council finally had control over the Grade II listed structure.

This statement seemed somewhat optimistic as a legal challenge to the ownership of Colwyn Bay’s Victoria pier was then made by its previous owner, Steve Hunt. The case was scheduled for a full day hearing. Work continued to make the pier safe and in August 2012 it was reported that a hearing at Cardiff Crown Court had ruled in the council’s favour. In November 2012, the courts also ruled against a separate claim of a ‘beneficial interest’ by Mr Hunt’s mother. But this was still not the end of the ownership dispute as in December 2012, an order was issued in the Royal Courts of Justice giving Mr Hunt permission to appeal against the earlier decision that it should not be handed back to him.

Meanwhile, the council and Shore Thing continued with their bid for HLF funds to restore the pier which it was announced would include plans for an arts centre and there was strong support for the remains of murals dating from the 1930s, by the artists Eric Ravilious and Mary Adshead, and which had been covered in both wallpaper and a thin layer of plaster, to be restored. The HLF bid for £5 million was submitted in March 2013.

April 2013 – Ownership battle ends up at High Court
April 2013 saw the continuation of the battle for ownership of the pier in an appeal at the High Court in London. The former owner, Steve Hunt, who had been made bankrupt in 2008 in a dispute over unpaid council tax and business rates, argued that the Victorian pier should have come to him three years after the bankruptcy. Mr Hunt’s mother also claimed that she still had an interest in the pier since she had paid over part of the money towards its purchase in 2003. Conwy council disputed both claims and judgement was reserved.

May 2013 – Permission given for ownership challenge
However, in May 2013, Sir William Blackburne subsequently ruled that Mr Hunt should get another chance to persuade a local judge that the pier, and the foreshore on which it stands, should be formally ‘vested’ in him. There would therefore need to be a re-hearing of the dispute at the County Court.

May 2013 – Pier lottery grant boosts restoration plans
Despite the continuing saga of the pier’s ownership, later in the month the Heritage Lottery Fund approved a grant of nearly £594,900 to be used by Conwy Council to develop plans for the full restoration of the pier. The grant would include restoration of the pier’s Art Deco pavilion, and would also allow the council to apply for more HLF funding to assist a bid for the full award of £4,379,600 to complete the scheme.

July 2013 – Colwyn Bay pier campaign gets underway
In July, the Victoria Pier Pressure Group and social enterprise Shore Thing announced a strategy involving awareness and fundraising events, including the Summer Grand Draw Raffle on Friday, July 26 at 5pm, drawn by Conwy Council chief executive Iwan Davies. More events were planned and the group aimed to establish a permanent presence in a portable cabin outside the pier to raise awareness.

September 2013 – Council approves £20,000 grant for pier
Then in September 2013, Colwyn Bay town councillors approved a £20,000 grant towards funding a professional design team to draw up final proposals for the restoration and development of the pier.

October 2013 – £65000 needed to preserve rare mural
An appeal was launched in October to raise £65,000 to preserve a rare mural created in the 1930s by Eric Ravilious and Mary Adshead which had been discovered covered in wallpaper and a thin layer of plaster in the crumbling pier building.

November 2013 – Pier’s condition ‘distresses everybody’…
In November, a report was presented to Conwy Council indicating that the restoration of the pier could cost £15,000,000. This immediately prompted discussions on whether the pier should simply be demolished instead of being restored. This would need the Grade II structure to be de-listed by heritage organisation, CADW.

December 2013
* Report says pier will cost £15m to restore

* Councillors to discuss demolition of pier

* Strong response to pier demolition possibility

* Pier demolition will be fought against

* Campaigners call for public’s support over pier

* Petition to save historic structure from demolition

Throughout December, the news that demolition of the pier was being considered generated a very strong response from businessess, local groups and members of the public. It was reported that demolition would itself cost in the region of £1,000,000 which would effectively be dead money. Nevertheless, despite vehement opposition within the town, Conwy councillors went ahead and voted to demolish the pier.

January 2014 – Councillors’ anger at not being consulted over pier
In January 2014, dozens of people were turned away from a packed meeting of the town council at which the director of pressure group, Shore Thing, reported that the business plan to save the pier had not even been seen by the full council. The ownership of the pier also had still not been decided and was awaiting a court case in August.

January 2014 – Pictures reveal the shocking state of pier
Later in the month, photos taken by Gavin Davies, director of Shore Thing, underlined the dereliction inside the pier, with bird droppings covering the interior of the main pavilion and rooms full of damaged junk and caved in ceilings. Nevertheless, Mr Davies remained confident that the pier could be saved.

February 2014 – Campaign group draws up fresh bid to save Pier
In February 2014, Conwy Council formally declined the HLF award of £594,900 which had been intended to develop the restoration plans. But Shore Thing announced that they were putting together a fresh bid to HLF to save the pier.

March 2014 – Final plea to save pier from demolition
A final plea to reverse the demolition of the pier was made in March 2014 by the Victorian Society who said that the £15,000,000 figure previously quoted was based on not just a restoration, but a major redevelopment of the structure and how it could function and there were much less costly options available. However, the likelihood remained that the council would still vote for demolition.

March 2014 – Cabinet votes to back pier demolition
But in the same month, it was reported that Conwy Council’s Cabinet members were being asked to vote for demolition of the pier, after a full council decision to have the pier de-listed on the grounds that redevelopment was not a viable option.

April 2014 – Ownership hearing postponed until June
In April 2014, it was reported that the court hearing between businessman Steve Hunt and Conwy Council which was due to take place next week had now been postponed until after June 6 due to problems with receipt of court papers.

June 2014 – Bid fails to have council removed from court
And in June 2014, an application by Mr Hunt in May to have Conwy Council removed from the on-going proceedings and, failing that, to have the council’s evidence struck out, was refused by a judge in Cardiff County Court, but Mr Hunt lodged an appeal to the High Court in England which meant that the hearing would now be delayed until August.

June 2014 – Pier group in new row with Conwy council
Also in June 2014, Gavin Davies from the Victoria Pier Trust claimed Conwy council was ignoring its requests for meetings and dialogue with the authority. Iwan Davies, Conwy County Council’s Chief Executive, said that they had not received any approach from the Victoria Pier Trust, a claim Mr Davies said was absolute rubbish.

August 2014 – Pier court hearing adjourned until autumn
In August, the much awaited court case between the council and Mr Hunt was again adjourned until the autumn. However, the council decide to continue with their strategy to have the pier removed, notwithstanding the outcome of the litigation.

September 2014 – Council presses ahead with demolition plans
So in September, Conwy council appointed independent environmental consultants Nash Partnership of Bath to advise and support its demolition bid. The consultant’s would test the merits of Conwy’s case for demolition, report monthly and conclude its work by November or December. Although the consultant was reported as already expressing doubt over the pier’s future.

October 2014 – Pier safety measures stepped up
With the pier continuing its fall into disrepair, in October Conwy Council applied for a marine licence to Natural Resources Wales to erect a fence “to protect the public from (the) risk of the unstable structure”.

October 2014 – Councillors back bid to revamp pier
But also in October, in direct opposition to the strategy of Conwy County Council, Colwyn Bay Town Councillors voted to submit a bid — likely to be about £8.5m — by the end of November to the Heritage Lottery Fund to redevelop the Grade II listed Victoria Pier and signed a “memorandum of understanding” to enter a partnership with the Colwyn Victoria Pier Trust in regards to the application.

November 2014 – Lottery funding bid to save Colwyn Bay Pier
November saw campaigners finalising a multi-million pound bid to the Heritage Lottery Fund to rescue the Victoria pier, a move backed by Colwyn Bay Town Council, which signed a “memorandum of understanding” to enter a partnership with the Colwyn Victoria Pier Trust in regards to the application. A decision on the application was thought could be made as early as April 2015.

December 2014 – Court case over future of Pier adjourned
In December the court proceedings on ownership of the pier were once again delayed “due to separate proceedings being brought by Mr Hunt in respect of a bankruptcy issue against another party”.

January 2015 – Pier at risk of imminent collapse
In January 2015, Conwy Council claimed the the pier was at ‘imminent risk of self-demolition’ and said the beach around pier had to be fenced off because of the risk of collapse.

February 2015 – Council legal fees mount-up
It was reported in February 2015 that Conwy Council’s legal costs in their dipute over the ownership of the pier would be likely to exceed £250,000, reportedly more than a third of the total upkeep figure. A further court hearing was due later in the year.

February 2015 – Conwy Council submit demolition plans for Colwyn Bay Pier
Also in February 2015, Conwy council submitted a planning application to demolish the pier, despite the there not having been a decision made by HLF on a multi-million pound grant to redevelop it.

March 2015 – HLF visit to Colwyn Bay Pier a success – decision to be announced on May 8th
In March, representatives of the Heritage Lottery Fund travelled to Colwyn Bay to view the Victoria Pier for themselves, and to hear a heartfelt plea from Colwyn Victoria Pier Trust for a £9.6m grant to redevelop it.

April 2015 – Decision looms for Colwyn Bay Pier
In April 2015, a decision on the £9.6million Heritage Lottery Fund application was expected to be made on 28th April, but the outcome would not be revealed until May 8 due to the upcoming General Election.

May 2015 – Heritage Lottery Fund rejects £9.6m redevelopment grant bid
The bid to redevelop the Victoria Pier was rejected by the HLF in May 2015, one of the reasons being the lack of “strong support” from Conwy Council. The HLF said that they had not received a clear enough indication of strong support from Conwy County Borough Council and in light of this, as well as the absence of other confirmed financial support and the potential for increased costs, the application was deemed high risk.

May 2015 – Colwyn Victoria Pier Trust vow to continue battle to save pier
Despite the setback of the £9.6million proposal to restore the Colwyn Bay pier being refused by Heritage Lottery Fund, members of the Colwyn Victoria Pier Trust began working on submitting a second bid in November.

June 2015 – Councillors vote to demolish pier
The saga continued in June 2015 when Conwy council’s planning committee said it was minded to grant conditional permission for demolition of the pier. However, the proposals still needed listed building consent.

June 2015 – Colwyn Victoria Pier trust to meet with Conwy Council to discuss pier’s future
Also in June, it was reported that a special council meeting had been arranged in which Conwy councillors would meet with members of the Colwyn Victoria Pier Trust, looking to redevelop the Grade II listed structure. The Pier Trust described the meeting as good news and an opportunity to make councillors aware of the full facts of the case.

October 2015 – Colwyn Bay Pier ownership battle goes to high court
The dispute over ownership of the pier, which had been contested for several years, reached the High Court in London in October 2015. Former owner, Steve Hunt, claimed the pier ownership should have reverted to him three years after he was made bankrupt but Conwy council argued that it passed to the Crown Estate before it signed a deal to buy the pier in 2012.

Conwy Council questioned over Colwyn Bay Pier
In February 2016, local MP, David Jones, strongly criticised Conwy council in its handling of the debacle over the pier. He said that the £250,000 in fees spent by the council could have been better spent on local services and questioned why the council bought Victoria Pier in the first place, when it now proposed to demolish it at an estimated further cost of £1m.

March 2016 – Campaign group chairman unveils new plan to save pier
In March 2016, Mark Roberts, the new chairman of the Colwyn Bay Victoria Pier Trust unveiled a new proposal to save the town’s Victoria Pier which involved the dismantling of the pier, as opposed to its demolition, in order to examine all of its components and their viability.Mr Roberts said the trust was already exploring funding channels to continue its work, and that discussions had been opened with Conwy Council to seek permission for dismantling the structure.

May 2016 – Conwy County Council undertake another inspection with a view to demolish Colwyn Bay Pier
An inspection of Colwyn Bay’s Victoria Pier was launched by Conwy BC in May 2016 to support its plans to demolish the pier. The pier, a Grade II listed building required government consent for any proposal to demolish and the council expressed the hope that the new survey would enable them to gain this consent.

August 2016 – Colwyn Bay promenade road closure for redevelopment
Work on the latest phase of Conwy CBC’s multi-million pound plans to regenerate the waterfront caused a 1km stretch of the promenade road to be closed and diversions put in place in August 2016. The development included widening, realigning and raising a section of the existing promenade, improving parking and new landscaping.

August 2016 – What is going on with Colwyn Bay Pier?
Also in August, the North Wales Daily Post published an update on Colwyn Bay Pier. A spokesman for Conwy CBC was reported as saying “The straight answer to ‘Will it ever be demolished’ is that the council hope it will, substantially. We want to see it demolished for health and safety and visual reasons to be able to re-open that section of the beach.”
However, Mark Roberts, chairman of the Colwyn Bay Victoria Pier Trust who are fighting hard to retain the pier, said: “No. Demolition is not an option, not until every avenue has been explored.” Mr Roberts said he was speaking not from a Trust perspective but as a former chief planning officer who is qualified in planning law.

August 2016 – Meeting over future of Colwyn Bay Pier agreed
Later in the month, it was revealed that a meeting to discuss the future of the pier had finally been agreed between the trust’s steering group and Conwy County Borough Council’s pier project board, but the date had yet to be finalised. Mark Roberts, CVPT chairman, said “Our case is progressing – We’re developing the scheme in more detail and undertaking a series of informal discussions with the council who have been very positive to date. We’ve engaged with experts in respective fields to undertake reports and assessments on our behalf, one or two of them world-leading.”

December 2016 – Ex-owner loses court bid but fight to save pier goes on
In December 2016 it was reported that businessman Steve Hunt had lost his final bid at the Court of Appeal for ownership of the pier and that the Court had ruled that he could not lodge a further appeal. Making a strong case against the demolition of the structure, Colwyn Bay Councillor David P Griffiths said “A restored pavilion at the expense of a Lottery Grant rather than the over-stretched Council Tax payer is clearly the solution for all, the plans being put forward by the Pier Trust being futuristic as well as heritage embracing will give every opportunity for entrepreneurs to come forward and invest in a thriving resort that again is going to be Colwyn Bay.”

December 2016 – Engineers make final assessments of Colwyn Bay pier ahead of demolition bid
Also in December 2016, engineers carried out the final part of the structural assessment on the pier, which Conwy County Borough Council were proposing to use to support the case for demolition in its forthcoming planning application.

December 2016 – Drone footage captures Colwyn Bay’s decaying pier
Later in the month, footage taken by a drone camera showed the result of the years of neglect and poor maintenance on the decaying pier.

January 2017 – Trust plans for pier soon to be announced
In January 2017, as Conwy CBC prepared to submit its second application for listed building consent to demolish the pier, the Victoria Pier Trust chairman, Mark Roberts, said the Trust would be unveiling their vision for the future of the pier at the end of the month.

January 2017 – Positive moves to save Colwyn Bay’s Victoria Pier
January also saw a more positive report in which Conwy Council council said it had a positive meeting with the pier trust and would now be dismantling and storing the structure with the possibility of a future rebuild.

February 2017 – End section of Colwyn Bay Pier collapses
The following month a large section of the pier at the seward end collapsed into the sea. Engineers began assessing the damage to the partially collapsed pier which had been fenced off for some time because of its deteriorating condition.

February 2017 – Conwy Council plans to dismantle and store Victoria Pier
Notwithstanding the collapse of the seaward section of the pier, February also saw Conwy Council confirm its plans to submit a Listed Building Consent application to dismantle the pier and then store the dismantled listed components for the Victoria Pier Trust to restore the pier in the future.

February 2017 – Collapsed section of Victoria Pier to be dismantled
The Council’s cabinet considered an urgent report later in the month which said that because of the risk of further collapse, the council could not wait for the listed building consent to be granted before removing the collapsed section of the pier. The council therefore voted to dismantle and remove this section. Work was expected to take about three weeks.

February 2017 – Storm Doris causes further Colwyn Bay pier collapse
At the end of February, high winds and waves generated by storm Doris, one of the worst to hit North Wales in recent years, caused a further collapse of the seaward section of the pier.

March 2017 – Dismantling work on Victoria pier begins
Welsh heritage body, CADW, and the Health and Safety Executive were monitoring the situation as the initial work to disconnect the collapsed section of the Victoria pier and the removal of materials commenced. The remainder of the seaward section would then be dismantled.

March 2017 – Restoration plan agreed for Colwyn Bay’s Victoria Pier
During March 2017, agreement was reached that the derelict Victoria Pier be redeveloped into a shortened boardwalk. Conwy council, which had originally been pressing for the demolition of the pier, also agreed to support the Colwyn Victoria Pier Trust (CVPT) bid to restore the pier, recreate the 1930s Art Deco pavilion, develop a new learning centre and install kiosks. The Heritage Lottery Fund had made it clear that the support of the council for the trust’s project would be an essential pre-requisite for any application for funding.

March 2017 – Exciting plans for the regeneration of Colwyn Bay Pier revealed!
Later in the month, the first images of a design concept for a restored Victoria Pier, including an open air cinema, an outdoor stage and a heritage centre, were unveiled at a public meeting by members of the Colwyn Bay Victoria Pier Trust.

May 2017 – Colwyn Bay Pier dealt funding blow by HLF
In May 2017, it was reported that an HLF representative had advised Colwyn Bay Victoria Pier Trust(CVPT) and Conwy CBC that funding from HLF was unlikely to be considered because piers were seen as high risk projects. CVPT were particularly aggrieved because they had been previously led to believe by HLF that the project to restore the pier would be considered for funding. HLF later appeared to back track from their statements about non-funding of piers.

July 2017 – Plans to dismantle Victoria Pier approved
In July 2017, Conwy Council’s planning committee granted permission for the Victoria Pier to be dismantled and a shortened boardwalk be rebuilt closest to the landward end. Retrospective permission was also given for a section which had already been dismantled on safety grounds.

August 2017 – Fight to save Colwyn Bay Pier continues apace
In August 2017, it emerged that a dialogue was continuing between Colwyn Bay Victoria Pier Trust(CVPT) and the Heritage Lottery Fund(HLF) on the future of the Victoria Pier. The result of Conwy Council’s application for Listed Building Consent to dismantle the pier as part of the initial stages of the restoration project was expected in September.

September 2017 – Asbestos concerns over Colwyn Bay Pier
Asbestos sheeting was used in the construction of the main pavilion in the 1930s. A report by Conwy council said the sheeting could break up if the pier was hit by bad weather and wanted to dismantle it as soon as possible.

October 2017 – Dismantling of Colwyn Bay Pier gains approval
In October 2017, the Welsh Government gave approval for the full dismantling of the Victoria Pier, enabling Conwy council to move ahead with proposed redevelopment plans.

November 2017 – Proposals being developed for dismantling and future restoration of Colwyn Bay Pier
Councillors reiterated their continued support of Colwyn Victoria Pier Trust, as the Trust continued to develop proposals and funding applications for the future restoration and re-creation of a more substantial, self-sufficient pier.

January 2018 – Dismantling of Colwyn Bay Pier begins
In mid-January 2018, it was announced that contractors would begin the dismantling of the old pier within weeks. The work was estimated to take four months.

February 2018 – Surveying of dismantled Pier pieces begins at Colwyn Bay
Parts of the pier having been removed carefully were being put into storage to be surveyed to be used in the reconstruction of the pier later this year.

March 2018 – Bid to save Colwyn Bay Pier’s famous murals
The following month, further details emerged on the work has being done to save as much of the murals from the pavilion of Colwyn Bay’s pier as it is demolished. Work by war artist Eric Ravilious and murals by painter Mary Adshead formed part of the decoration inside the art deco pavilion when it was constructed in 1934. Experts initially said the murals would be impossible to remove but staff were working to retain them.

April 2018 – Colwyn Victoria Pier Trust energised after successful AGM meeting
In April 2018, the North Wales Pioneer reported that the Victoria Pier Trust had held its AGM on Wednesday, March 28 where discussions were held around the development of the ongoing scheme for the Colwyn Bay Pier, progress with the dismantling and the working relationship with the Conwy County Borough Council.

April 2018 – Dismantling at Colwyn Bay sees Pier split in two
Contractors pulling down Colwyn Bay’s Victoria Pier during April divided the structure to guard against fire breaking out during the dismantling work. The project was reported as making good headway.

May 2018 – Dismantling of Colwyn Bay Pier set to be complete by June
In May 2018, it was reported that dismantling of the Colwyn Bay Pier should be completed by mid-June. The Colwyn Victoria Pier Trust had been working closely with the Conwy County Borough Council and were currently working to put together their own scheme, which Trust chairperson, Mark Roberts, said was in its initial phase and that he was hoping to put it to public consultation as soon as possible.

May 2018 – Dismantling of Colwyn Bay Pier completed
Later in the month, BBC Wales broadcast a video of the final dismantling of the pier.

June 2018 – Exciting times ahead for Colwyn Bay Pier
June 2018 saw news that Conwy County Borough Council (CCBC) were soon to reveal the successful bidder for the tender process to build a truncated pier on the site while designers were formulating proposals for its appearance.Meanwhile, the Victoria Pier Trust were exploring plans to extend the Pier once the truncated version was installed. Victoria Pier Trust chairperson, Mark Roberts, said plans for a new Pier in Colwyn Bay had never been so advanced.

July 2018 – Design of new truncated pier reaches the next stage
In July 2018 it was announced that Donald Insall Associates had been awarded the contract to draw up the detailed construction designs for the new truncated pier. It was hoped that work on the pier could commence in Spring 2019. The Council reiterated its support of Colwyn Victoria Pier Trust, which are developing proposals for the future restoration and re-creation of a more substantial pier.

September 2018 – New home needed for Colwyn Bay Pier murals
The Colwyn Victoria Pier Trust were working closely with Mt Davies in trying to find somewhere safe to continue to store the murals, but had still had no luck.

Read More

December 2018 – Home found for Colwyn Bay Pier murals
The murals, that were a part of the Colwyn Bay Victoria Pier for more than a century, were set be scrapped with just a couple of reference panels kept if a long term home was not found for them.

Read More

March 2019 – Colwyn Bay Pier reconstruction plans get underway
A Conwy Council spokeswoman said: ” We’re intending to go out to tender for the construction work by the end of March, with the aim of work starting on site later this year, with completion in 2020.

Read More

July 2019 – Work on new truncated pier at Colwyn Bay to begin!
It was reported that the new decked area will be about 43m (141ft) in length. The work was expected to take 30 weeks. Contracts had been awarded to two firms to build the structure using refurbished metalwork from the pier.

Read More

November 2019 – The rebuild of Colwyn Bay Pier begins!
Contractors started preparatory work to build the truncated pier at Colwyn Bay. The lower part of the promenade had been closed and fencing erected so that sand blasting work could take place on the columns, and groundworks carried out.

Read More

November 2019 – Further progress at Colwyn Bay. At only 45 metres it will be the second shortest pier in the UK, but we’ll be cherishing every inch!
The lower part of the prom was closed and fencing erected around the site so sand blasting work can take place on the columns. Work to prepare the ground ready for the new structure was also being carried out. The structural steelwork was expected to be delivered to the site in January.

Read More

July 2020 – Building work for the new Pier at Colwyn Bay restarts!
In July 2020 – although originally scheduled to be completed in the summer, scaffolding was erected and work resumed on the new, 45 meter truncated Colwyn Bay pier. The timetable for the project was carried-forward and was scheduled to be completed early 2021.



Colwyn Bay Pier News / Blog

By M Austin January 18, 2025
Llandudno Pier repair work continues- this is when it could reopen, (This is great news) LLANDUDNO PIER could reopen in some capacity this coming weekend, with most of its businesses to remain closed until February. The famous Victorian-era landmark was devastated by Storm Darragh in early December, with Kelly's Ice Cream parlour "completely” swept away , while a 150-year-old unit was "ripped off its foundations", with storm damage totalling an estimated £250,000. Llandudno Pier, which is owned by Tir Prince Leisure Group, have given an update on the work which has already been undertaken at the site. The gentleman’s toilet block will have its roof replaced, as the footing for the Kelly’s unit now been cleared and made safe. The roof to the bar at the end of the pier is currently being repaired after several sections were blown o One hut remains on its side, with another impacted hut requiring surveying. “Several” benches and tables which were damaged are in the process of being repaired, and repairs will shortly start on the steel work supporting the structure – 10-12 pieces under the café, bar and deck arcade were “significantly” damaged and will need replacing or reattaching. “The weather hasn’t helped in any way with the progress of the repairs and we have faced several hurdles so far as a result,” said Paul Williams, Llandudno Pier general manager. “We are looking at opening up the Pier as far as the The Crystal Hut by next weekend. “The shops will remain closed until February 1 and then hopefully back fully trading for the upcoming season. “We are trying our hardest to get the Pier back open fully as quickly, but as safely, as possible. “On behalf of the whole team, I would like to thank everyone for all their continued support, it’s greatly appreciated. I look forward to to welcoming everyone back in the coming weeks.” Thisarticle is from the North Wales Pioneer see HERE
By MD Austin January 6, 2025
A big Thank you to TAPE who have created this fantastic model of the new Pier, which is now on display in a shop window, near the entrance to the Bay View Shopping Centre, Colwyn Bay, About TAPE (Priding itself on accessibility and inclusivity TAPE has been providing high-quality inclusive. supportive, person-led opportunities since 2008. From 1-hour taster sessions and film screenings to commercial contracts and feature film production TAPE’s delivery offers people the chance to explore and develop their creativity. TAPE’s delivery supports both individuals and groups, working with people of all ages and experience levels, ensuring that they are centrally involved in the creative process. From first time creatives through to graduates and professionals the charity can offer training, support and opportunities.) see their website HERE
By M Austin December 7, 2024
Heartbreaking news, as Llandudno Pier has been damaged by a 93mph gales! The owner of Llandudno's historic pier says it will be a "miracle" if it survives Storm Darragh. North Wales has been battered by fierce winds since the early hours of the morning - reaching 93mph in some areas. The famous pier has already suffered damage in the storms. One kiosk has been ripped from its foundations while others have suffered roof damage. But the biggest fear is once high tide is reached at the resort. If wind speeds remain very high this could see the whole structure swamped. High tide is at 2.42pm this afternoon. Wind speeds are expected to remain at close to 70mph in Llandudno for much of the afternoon, with gales blowing in from the north. Adam Williams, of Tir Prince, who has owned the site since 2015, said: "The weather is biblical. We have never known it so bad. The tide still has a long way to come in yet, if it survives it will be a miracle. "I am thankful we spent so much money over the summer reinforcing the underneath. It’s heart breaking to watch, so much good work can be undone in the space of a few hours.At 2,295 feet (700 m), the pier is the longest in Wales and the fifth longest in England and Wales. It attracts millions of visitors every year. Thank you to the Daily Post for this story. To read the article please see HERE
By M D Austin December 3, 2024
The Pier Trust Fundraising Shop. 18 Station Road are having a sale. Books 10p each, DVDs 10p each, Clothing from 10p each, Ceramics from 10p each, Bedding from 10p each and much more, We will be open this week, Tues, 10-3pm, Wed, Thurs Fri, am and Sat 9-4pm, pop down and grab a bargain. (Please do not worry we are not closing down!)
Show More